Question: Enabled: Topic 2 Quiz Saved Help Save Exit Submit You have just used the network planning model and found the critical path length is 30

Enabled: Topic 2 Quiz Saved Help Save Exit Submit You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. What is the probability that the project will be completed in 33 days or less equal to? (2 decimal accuracy). Multiple Choice 0.73 0.55 O 0.12 0.27 O 0.60 3 W E R U O P S G H K X C V B N M