Question: End (1) (3) A (2) [1] B (3) (4) C (2) (1) D (4) (3) E (3) [2] F (4) (3) G (2) [2] H

End (1) (3) A (2) [1] B (3) (4) C (2) (1) D (4)
End (1) (3) A (2) [1] B (3) (4) C (2) (1) D (4) (3) E (3) [2] F (4) (3) G (2) [2] H (3) [1] F (2) (3) G (3) [2] Item End A B D E On Hand 54 74 82 65 561 390 1346 2173 489 (Lead Time Direct Components 3 A2, B3, C2 1 D4, E3 4 F4, G2 1 H3 2 2 3 2 1 F2, G3 F G H If the 300 "End" items are required in 24 weeks, what is the latest week work can begin to meet that dealine