Question: Engineering Economics Evaluation of two projects: A and B Assuming that MARR=8 % and based on the given information in the summary table below, compare
Engineering Economics Evaluation of two projects: A and B Assuming that MARR=8 % and based on the given information in the summary table below, compare the Project A and B using: 9.1. Present Worth Net Benefit; and
9.2. Simple Payback Period.
| Parameters | Project A | Project B |
| Initail Costs ($) | 200,000 | 400,000 |
| Annual Net Revenue ($/yr.) | 50,000 | 70,000 |
| Project Lifetime (Yrs.) | 5 | 10 |
| Salvage at Lifetime ($) | 20,000 | 50,000 |
For both projects draw the cash flow diagrams and cash flow tables.