Question: ENGR - 4 2 9 - Homework No . 4 Sp - 2 0 2 4 A . Use the data from the table below

ENGR-429- Homework No.4
Sp-2024
A. Use the data from the table below to draw the precedence network. Then do the CPM calculations and complete the table below. You must clearly show the critical path. Assume that all activities are contiguous.
\table[[ct,Dur,IPA,Relation,Lag,ES,EF,LS,LF,TF,FF],[A,10,--,,,,,,,,],[B,2,A,SS,1,,,,,,],[,,A,FF,2,,,,,,],[C,12,B,SS,3,,,,,,],[,,B,FF,2,,,,,,],[D,3,C,SS,2,,,,,,],[,,C,FF,2,,,,,,]]
B. Repeat the problem in A, assuming that all activities are interruptible. You must show the critical path and whether the activities are critical, partially critical, or non-critical.
\table[[Act,Dur,IPA,Relation,Lag,ES,EF,LS,LF,TF,SRF,DRF],[A,10,--,,,,,,,,,],[B,2,A,SS,1,,,,,,,],[,,A,FF,2,,,,,,,],[C,12,B,SS,3,,,,,,,],[,,B,FF,2,,,,,,,],[D,3,C,SS,2,,,,,,,],[,,C,FF,2,,,,,,,]]
ENGR - 4 2 9 - Homework No . 4 Sp - 2 0 2 4 A .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!