Question: ENM 2 6 0 1 AUGUST 2 0 2 4 for each task as listed in the table below: table [ [ Task ,

ENM2601
AUGUST 2024
for each task as listed in the table below:
\table[[Task,Duration (Days),Predecessor],[A,6,-],[B,10,-],[C,5,A],[D,14,A],[E,20,B],[F,4,C],[G,2,D],[H,21,E],[I,17,E],[J,11,G],[K,30,I],[L,40,F, H, J, K]]
Use the above-mentioned information to do the following:
a) Design a project-network diagram.
b) Demonstrate all the paths through the diagram, and their duration.
c) Demonstrate the critical path and the duration.
[17]