Question: Ensuring that project activities are defined as work packages that can be completed by a specific worker or team is an essential part of what
Ensuring that project activities are defined as work packages that can be completed by a specific worker or team is an essential part of what aspect of project planning?
Multiple Choice
Defining project scope
Risk management planning
Work breakdown structure
Project scheduling