In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working:
\table[[Activity,Immediate Predecessor(s),Time (days)],[A,-,3],[B,A,4],[C,A,6],[D,B,6],[E,B,4],[F,C,4],[G,D,6],[H,E, F,8]]
The correct precedence diagram for the project is shown in