Question: Enter GO 12. For these two mutually exclusive projects, graph the NPV profile and show and calculate the crossover rate. Determine which project is better

 Enter GO 12. For these two mutually exclusive projects, graph the

Enter GO 12. For these two mutually exclusive projects, graph the NPV profile and show and calculate the crossover rate. Determine which project is better at different interest rate levels. (You must show the two intercepts of the two projects in the graph, and the crossover rate). (50 points) Time Project A Project B 0 -3000 -2500 1 1000 1000 2 1500 2000 3 2000 1500 2000 1500 1000 500