Question: Enter task, durations and dependencies into MS Project? How do you enter this info into MS Project? Activity Preceding Activity Time (Weeks) A 4. B

Enter task, durations and dependencies into MS Project?
Enter task, durations and dependencies into MS
How do you enter this info into MS Project? Enter task, durations and dependencies into MS
Activity Preceding Activity Time (Weeks) A 4. B 6 A, B 7 D B 8 E B 5 F 5 G D 7 H D, E 8 I F, G, H 4 TUI Callu Time (Weeks) Activity Preceding Activity 4 A 6 B 7 A, B B. D 8 E B. 5 F 5 G D 7 H D, E 8 I F, G, H 4