Question: Entity A commenced a contract to build a bridge for Entity B in the year ended 30 September 2020. The contract price was agreed at
-
Entity A commenced a contract to build a bridge for Entity B in the year ended 30 September 2020. The contract price was agreed at $2,800 million and the total expected costs of the contract have been confirmed as $1,500 million.
Entity A will satisfy the performance obligation over time.
The following figures were correctly recognised in the Statement of Profit or Loss for the year ended 30 September 2020:
- Revenue $1,000 million
- Cost of Sales $480 million
- Profit $520 million
The following figures are also relevant in relation to this contract:
- 2020 2021
- Million Million
- Costs incurred to date $660 $1,020
- Work certified to date $880 $2,100
Entity A recognises progress on a work certified basis.
REQUIRED:
Measure the contract revenue and contract cost for Entity A in its Statement of Profit or Loss for the year ended 30 September 2021.
ANSWER:
Contract revenue = $ Million
Contract cost = $ Million