Question: Entity A commenced a contract to build a bridge for Entity B in the year ended 30 September 2020. The contract price was agreed at

  1. Entity A commenced a contract to build a bridge for Entity B in the year ended 30 September 2020. The contract price was agreed at $2,800 million and the total expected costs of the contract have been confirmed as $1,500 million.

    Entity A will satisfy the performance obligation over time.

    The following figures were correctly recognised in the Statement of Profit or Loss for the year ended 30 September 2020:

    • Revenue $1,000 million
    • Cost of Sales $480 million
    • Profit $520 million

    The following figures are also relevant in relation to this contract:

    • 2020 2021
    • Million Million
    • Costs incurred to date $660 $1,020
    • Work certified to date $880 $2,100

    Entity A recognises progress on a work certified basis.

    REQUIRED:

    Measure the contract revenue and contract cost for Entity A in its Statement of Profit or Loss for the year ended 30 September 2021.

    ANSWER:

    Contract revenue = $ Million

    Contract cost = $ Million

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!