Question: Entity - level controls can have a pervasive effect on the entity's ability to meet the control criteria. Which one of the following is not
Entitylevel controls can have a pervasive effect on the entity's ability to meet the control criteria. Which one of the
following is not an entitylevel control?
Multiple Choice
controls to monitor results of operations
the periodend financial reporting process
management's risk assessment process
controls to monitor the inventory taking process