Question: Equation sheet. Make sure units are as asked in a question. V = L A 1 + A 2 2 Grade in % : (

Equation sheet. Make sure units are as asked in a question.
V=LA1+A22
Grade in %: (100%)(vertical distance divided by horizontal distance)
Swell factor =1+ swell percentage ?100; loose volume l.e. Icy)= bank volume x swell Factor
Shrink factor shrink %100 : compacted volume (i.e.ccy)= bank volume x shrink factor
Ideal dozer production, in loose cubic yards per hour (Icy/hr): Blade capacity 60(min/hr)/(MT + LT + RT), where MT is maneuver time, LT is loaded time, and RT is return time, in minutes
Efficiency: Factor between 0 and 1, if in % divide by 100 to use with a formula. Could be expressed in minutes out of a total of 60 minutes per hour, or given as a %, or already as a factor.
Real dozer production, adjusted for efficiency = Ideal dozer production Efficiency
Total production cost = Owner and Operation cost + Wage cost
Equivalent grade from rolling resistance:
Grade G; in %=[Rolling resistance in (Ib/US ton)]/[20(lb/US ton)]
Effective grade = Grade resistance + rolling resistance
Conversions: 1ft=12in;1ft2=144in2;1yd=3ft;1yd3=27ft3;1 mile =5280ft1 hour =60 minutes, 1 minute =60 seconds, 1 hour =3600 seconds
Equation sheet. Make sure units are as asked in a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!