Question: ERP and Control: Please show work clearly, step by step in excel. An office supply company makes notebooks with two product structures: Pad and Cover.

ERP and Control:
Please show work clearly, step by step in excel.
An office supply company makes notebooks with two product structures: Pad and Cover. The standard labor hours for these are 2 and 3 hours, respectively. The items are made in two work centers: production and assembly, where the average percentage of work has been 65% for production and 35% for assembly. Note that these are the CPOF. Given the following schedule for the next 6 weeks, calculate the weekly labor hours needed in each of the two work centers. Week 1 2 3 4 5 6 Pad 45 40 37 25 18 22 Cover 70 50 42 55 58 62
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!