Question: ES for Activity 1 is 0 ES for Activity 2 is 0 ES for Activity 3 is 0 ES for Activity 4 is 4 ES

ES for Activity 1 is 0
ES for Activity 2 is 0
ES for Activity 3 is 0
ES for Activity 4 is 4
ES for Activity 5 is 5
ES for Activity 6 is 9
Resource requirements per activity are:
Activity 1: 3 resources
Activity 2: 1 resource
Activity 3: 1 resources
Activity 4: 1 resource
Activity 5: 3 resources
Activity 6: 2 resources
Duration per activity:
Activity 1 is 3
Activity 2 is 4
Activity 3 is 5
Activity 4 is 4
Activity 5 is 4
Activity 6 is 3
Late finish for each activity are:
Activity 1 is 5
Activity 2 is 5
Activity 3 is 5
Activity 4 is 9
Activity 5 is 9
Activity 6 is 12
Slack for each activity is :
Activity 1 is 2
Activity 2 is 1
Activity 3 is 0
Activity 4 is 1
Activity 5 is 0
Activity 6 is 0 S
Schedule resource load chart with ES and slack updates
\table[[ID,Resource,Duration,ES,LF,SL,TP 1,TP 2,TP 3,TP 4,TP 5,TP 6,TP 7,TP 8,TP 9,TP 10,TP 11,TP 12,TP 13,TP 14,TP 15],[1,3,3,0,5,2,,,,,,,,,,,,,,,],[2,1,4,0,5,1,,,,,,,,,,,,,,,],[3,1,5,0,5,0,,,,,,,,,,,,,,,],[4,1,4,4,9,1,,,,,,,,,,,,,,,],[5,3,4,5,9,0,,,,,,,,,,,,,,,],[6,2,3,9,12,0,,,,,,,,,,,,,,,],[Resources scheduled,,,,,,,,,,,,,,,],[Resources available,4,4,4,4,4,4,4,4,4,4,4,4,4,4,4]]
 ES for Activity 1 is 0 ES for Activity 2 is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!