Question: Eskom has offered a sobering update on the difficulties it is having at its Medupi and Kusile coal projects, which are not only years behind
Eskom has offered a sobering update on the difficulties it is having at its Medupi and Kusile coal projects, which are not only years behind schedule and significantly over budget but are now also beset with technical defects that are resulting in a serious underperformance of the four units that have entered into commercial operation. Officially Medupi is expected to cost Rbillion to build and Kusile Rbillion. The projects are twoandahalf times more expensive than what was initially budgeted and are well behind schedule, with the last Medupi unit expected in late or early and the last Kusile unit by mid
In a presentation delivered during the National Energy Regulator of South Africa Nersa public hearing in Soweto on Friday, technology GM Dr Titus Mathe reported that the three Medupi units and the one Kusile unit currently in commercial operation had, for the financial year to date, experienced a total of unit trips. Medupi unit trips rose from during the financial year to in the financial year, which runs to March He also revealed that the average energy availability factor EAF for the Medupi units was below between April and December last year, with Unit which was the first unit to enter into commercial operation in having been shut for repairs for three months from the start of September to the end of November.
The immediate target is to return to an EAF of which is woll below the 'uso requirement specification' target set for the units. Earlier this year Eskom indicated that the resumption of loadshedding in late was partly the result of the underperformance of those Medupi and Kusile units that had been brought into commercial operation. While Eskom initially described the poor performance of the units as "teething problems", Public Enterprises Minister Pravin Gordhan indicated that they could be more fundamental, particularly in relation to the performance of the boilers, the gninding mills and the fabric filters. A forensic investigation was instituted in in a bid to understand the problems. Mathe confirmed that major design and technical problems had been discovered, most of which related to the boilers. Some of the technical issues identified include:
The boiler spray systems being unable to cope, owing to a design that has resulted in higherthanexpected temperatures at the reheater. Excessive wearing of fabric filter plant bags, which is resulting in ash blockages. trips, load losses and emissionsrelated losses
Excessive wearing of fabric filter plant bags, which is resulting in ash blockages, tips, load losses and emissions
related losses
The milling plants at Medupi are failing to meet technical requirements, which has halved the time between
servicing intervals, negatively affected coal quality and has resulted in partial load losses.
The gas air heater performance and fouling is not meeting technical requirements. Problems with the dust handling plant, which is leading to high ash accumulation, leaks and more frequent maintenance, which is resulting in a lack of spare parts.
maintenance, which is resulting in a lack of spare parts.
Hardware failures on the distributed control system at two Medupi units is leading to trips.
And high vibrations on the generator auxiliary cooling loop.
Eskom had established a specialist team to develop solutions to rectify major defects and work streams had been established with contractors to jointly evaluate solutions. Mathe insisted that Eskom "knows exactly what the challenges are and said that detailed plans are in place to address the unit trips. He added that Eskom expected to have technical solutions for all the defects within the coming six months. It would then enter into commercial negotiations with contractors regarding liability for the defects and on how the repairs will be implemented.
He warned that some of the repairs would require the units to be on outage, which meant that the defects would probably be repaired in phases from around onwards. The timetable for the remaining Medupi and Kusile units had been slightly extended. The final completion date for the last Medupi unit had been shifted to November from May while Unit at Kusile was still expected to be finalised by June
The management of Eskom has since established that there is a need for the adoption of a quality philosophy within the organisation that will result in the attainment of optimal quality, and which will also ensure that customer requirements are easily defined and satisfied. Considering this, provide recommendations on the philosophy and or practices that can be adopted in facilitating these improvements. Make use of relevant quality frameworks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
