Question: Essay 1. The difference between design capacity and effective capacity 2. Assumptions from the Break Even analysis: 3. What can the operations manager do to

Essay
1. The difference between design capacity and effective capacity
2. Assumptions from the Break Even analysis:
3. What can the operations manager do to deal with bottleneck operations?

Problem 1
Markland Manufacturing intends to increase capacity by overcoming bottleneck operations by adding new equipment. Two vendors have submitted proposals. The fixed fee for proposal A is $ 50,000, and for proposal B, $ 70,000. 

The variable cost for A is $ 12 and for B, $ 10. The income generated by each unit is $ 20.
a) What is the break-even point in the unit for proposal A?
b) What is the break-even point in the unit for proposal B?

Problem 2
3 work stations illustrated in the following figure have a product that must go through one of the two machines at station 1 (parallel) before proceeding to station 2.
"The attached image"

Station 1 Machine A Capacty: 20 units/hr Station 2 Station 3 Stationa) What is the system jam?

b) What is the bottleneck station of this work cell?
c) Throughput time?
d) If the company operates 10 hours per day, 5 days per week, what is the weekly capacity of this work cell?

Station 1 Machine A Capacty: 20 units/hr Station 2 Station 3 Station 1 Capacty. 5 units/hr Capacity: 12 unitshr Machine B Capacity: 20 units/hr

Step by Step Solution

3.44 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Problem 2t... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!