Question: Estimate at Completion ( EAC ) is how much we actually spent for work completed. how much of the budget we have left to spend

Estimate at Completion (EAC) is
how much we actually spent for work completed.
how much of the budget we have left to spend on the project.
how much we budgeted to spend at the beginning of the project.
how much of the budget we really should have spent on the work completed so far.
how much we expect to spend at the conclusion of the project based on the current project's performance.
 Estimate at Completion (EAC) is how much we actually spent for