Question: Estimate the project's operating cash flows. What are the project's NPV, IRR, modified IRR, and Payback? These are the answers provided, but I want to
Estimate the project's operating cash flows. What are the project's NPV, IRR, modified IRR, and Payback?
These are the answers provided, but I want to know the step by step computations:
NPV = ($87,618)
IRR = 8.3%
MIRR = 9%
Payback = 3.3
Reference: Robert Montoya, Inc. case