Question: estimated to be 50,UW lines ol coue. 2. Using the following job log, calculate all of the basic measures and the progress indicators. Is the

 estimated to be 50,UW lines ol coue. 2. Using the following

estimated to be 50,UW lines ol coue. 2. Using the following job log, calculate all of the basic measures and the progress indicators. Is the project on schedule? Assume that it is currently 3/1/01. Actual Effort So Far days) 70 20 Estimated Effort (programmer(programmer- Estimated Actual Date Work Task days) Completion Date Completed 1/15/01 2/15/01 2/25/01 4/15/01 6/1/01 7/1/01 2/1/01 2/15/01 3/1/01 4/1/01 50 2 35 3 20 40 40 10 80 20