Question: estimated to be 50,UW lines ol coue. 2. Using the following job log, calculate all of the basic measures and the progress indicators. Is the

estimated to be 50,UW lines ol coue. 2. Using the following job log, calculate all of the basic measures and the progress indicators. Is the project on schedule? Assume that it is currently 3/1/01. Actual Effort So Far days) 70 20 Estimated Effort (programmer(programmer- Estimated Actual Date Work Task days) Completion Date Completed 1/15/01 2/15/01 2/25/01 4/15/01 6/1/01 7/1/01 2/1/01 2/15/01 3/1/01 4/1/01 50 2 35 3 20 40 40 10 80 20
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
