Question: ____________ estimating uses values, or attributes, of a previous project that are similar to the current project. Values and attributes of the projects may include
____________ estimating uses values, or attributes, of a previous project that are similar to the current project. Values and attributes of the projects may include but are not limited to: scope, cost, budget, duration, and measures of scale (e.g., size, weight). Comparison of these project values, or attributes, becomes the basis for estimating the same parameter or measurement for the current project. Question 3 options: Parametric cost Bottom-up cost Three-point cost Analogous cost