Question: estion Completion Status: QUESTION 1 Q/1 For a small Engineering project listed below: 1) Draw the Early Start project schedule using Time- scaled network 2)

estion Completion Status: QUESTION 1 Q/1 For a

estion Completion Status: QUESTION 1 Q/1 For a small Engineering project listed below: 1) Draw the Early Start project schedule using Time- scaled network 2) find a) Average daily requirement b) Effectiveness c) If the maximum available resource is 7 find Criticality index Activity Predecessor Duration (Days) Resource, Worker/day A 3 3 C A 4 5 D A 2 2 E 5 4 B C.D 4 1 F BE 7 6