Question: EUsing the worksheet. what is the cost for a E00 MRP strategy? Note: round your EOG calculation to the nearest whole number {no fractions of

EUsing the worksheet. what is the cost for a E00 MRP strategy? Note: round your EOG calculation to the nearest whole number {no fractions of units] Answer format is W without the S symbol or a comma separator. Setup Cost 2 SBSDl'order; Inventory Holding Cost 2 $2.50 per part per week; Leadtirne : 1 week EEOC}- r" -IIH-In 12 Gross Requirements 80 35 80 65 Scheduled Receipts Projected OH = 50 Net Requirements Planned Order Reoeipts Planned Order Releases 50
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts