Question: EV 9 - 1 table [ [ Activity , table [ [ Normal ] , [ Time ] ] , table [

EV9-1
\table[[Activity,\table[[Normal],[Time]],\table[[Normal],[Cost]],\table[[Maximum],[Crash Time]],\table[[Crash],[Cost]]],[A,1,100,0,0],[B,3,150,2,100],[C,4,200,1,50],[D,3,200,1,60],[E,4,200,2,70],[F,3,150,1,90]]
Total Direct Cost:Optimum Cost-Time Schedule
Project Duration Direct Costs
Indirect Costs Total Costs
121000
11925
10850
9775
8700
 EV9-1 \table[[Activity,\table[[Normal],[Time]],\table[[Normal],[Cost]],\table[[Maximum],[Crash Time]],\table[[Crash],[Cost]]],[A,1,100,0,0],[B,3,150,2,100],[C,4,200,1,50],[D,3,200,1,60],[E,4,200,2,70],[F,3,150,1,90]] Total Direct Cost:Optimum Cost-Time Schedule Project Duration Direct

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!