Question: Evaluate the three staternents below about project risks, and then choose the correct alternative: 1-The risk register is a component of the project management plan

Evaluate the three staternents below about project risks, and then choose the correct alternative: 1-The risk register is a component of the project management plan that describes how risk management activities will be structured and performed on a project. II-The risk register is a living document and new risks can be added as they are discovered. III-When complete, the risk register presents the results of both qualitative and quantitative risk analysis as well as risk response planning