Question: Evaluation of project team performance tends to be based on achieving project objectives according to _ _ _ _ _ _ . Group of answer
Evaluation of project team performance tends to be based on achieving project objectives according to
Group of answer choices
time.
cost
specifications.
customerend user satisfaction.
All of these alternatives are correct.