Question: evelop a material requirements plan for end item P and its components, given the following tree. Assume that all lead times are one week, and
evelop a material requirements plan for end item P and its components, given the following tree. Assume that all lead times are one week, and that lot-for-lot ordering is used except for item F, which is ordered in multiples of 100 units. One hundred units of P should be available at the start of week 4 and at the start of week 8. Beginning inventories are: 50 Ps, 80 As, and 100 Fs. Scheduled receipts are: 500 Fs at the start of week 1.
Please plug it in the table.
| Week Number | |
| Gross Requirements | |
| Scheduled Receipts | |
| Projected on hand | |
| Net requirements | |
| Planned-order receipt | |
| Planned-order release |
| Beginning LT1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |