Question: Every help is appreciated. Please use below information to create a Budget for the School Library Renovation. Project cost estimate: Hourly wage rates Project Manager

Every help is appreciated.

Please use below information to create a Budget for the School Library Renovation.

Project cost estimate:

Hourly wage rates

Project Manager (PM) wage rate is $75/hr

Architect hourly billing rate is $120/hr

School employee wages are not included in the project budget

Material costs

Demolition lump sum cost is $15,000

Wall construction lump sum cost is $25,000

Mechanical and Electrical systems lump sum cost $35,000

Painting and carpet installation lump sum cost is $25,000

Furniture costs

Room #1 furniture cost is $12,400 (includes tables, chairs and computer stations)

Room #2 and #3 furniture cost is $7,500 for each room (includes lecture stands and mobile desks)

Every help is appreciated. Please use below information to create a Budget

Please follow below Excel Sheet as a reference to fill out the above provided information.

for the School Library Renovation. Project cost estimate: Hourly wage rates Project

Work package Notes Duration (days) 3 1.1 Stakeholder interviews PM works four (4) hours on each of the three days 1.2 Architect selected 1 PM works two (2) hours 1.3 Concept plans created 3 1.4 Concept plan meeting 1 1.5 1.6 Design approved Furniture ordered 1 1 1.7 2.1 General contractor selected Building permit received 1 2 2.2 Demolition 4 2.3 Walls constructed 3 Architect bills for six (6) hours on each of days one and two and four (4) hours on the third day PM works four (4) hours and Architect bills for four (4) hours PM works three (3) hours PM works two (2) hours (ordering material) and manufacturer requires 50% deposit on material cost PM works two (2) hours PM works three (3) hours on day one and one (1) hour on day two PM works four (4) hours on days one and four Architect bills for (4) hours on days one and four General contractor submits bill for Lump Sum price estimate PM works four (4) hours on day three Architect bills for (4) hours on day three General contractor submits bill for Lump Sum price estimate PM works four (2) hours on days three and five General contractor submits bill for Lump Sum price estimate PM works four (4) hours on days one and four General contractor submits bill for Lump Sum price estimate PM works six (6) hours Architect bills for four (4) hours PM works for three (3) Manufacturer submits bill for the remaining 50% PM works five (5) hours PM works two (2) hours Architect bills for six (6) hours 2.4 M/E systems installed 5 2.5 Painting/carpet completed 2 2.6 Final inspection 1 3.1 3.2 3.3 3.4 Furniture delivered Furniture installed Stakeholder walkthrough Project closeout 1 2 1 1 Budget Baseline Proj: Stakeholders/Functions Employees Subs Material PM PM: Date: Enter $/hour for each Stakeholder/Function Total Enter total amount for each WBS work package Budget Task Name WBS ID 1.1 1.2 1.3 1.4 1.5 Total

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!