Question: Everything else is correct, except for the slack on Activity D. I've tried 0 and 4 days and those were both incorrect. EX6-7 (Algo) The
Everything else is correct, except for the slack on Activity D. I've tried 0 and 4 days and those were both incorrect. 
EX6-7 (Algo) The project information for the... The project information for the custom order project of the Air Control Company is presented here. Compute the early and late activity times and slack times. Identify the critical path. How many days will the project take