Question: EVM Example Week 7 . xlsx Directions - Step 1 : using the data from the Excel spreadsheet ( EMV _ Example _ Week 7
EVM Example Weekxlsx
Directions Step : using the data from the Excel spreadsheet EMVExampleWeek
Calculate the forecasting parameters through the end of the project ie EAC, ETC,
VAC use Formula # from the slide deck to calculate EAC
Question #: Based on your estimates, what would be your recommendations for
managing the project at the end of Week
Directions Step : Update the Excel spreadsheet with the information through Week
see table from the lecture slide
Calculate the performance value metrics ie CV SV CPI, SPI, EAC for Week
Present the EV performance graph for Week
Question #: How do the project's final weeks compare with the recommendations
you made at the end of Week
Submit a page summary of your answers to Questions and
Page EV performance graph and answer to Question #
Page Updated EV performance graph and answer to Question #
Submission requirements:
Written in full sentences
Proper spelling and grammar
Times New Roman point font, margins, doublespaced
Grading points total
Copy of EV performance graph and narrative response to Question # points
Copy of updated EV performance graph and narrative response to Question #
points
Narrative follows formatting requirements points
Project Title
Company Name Logo
Earned Value Analysis Report
Prepared By: Alex Zylka
Date:
For Period:
Week
Summary:
Use this space to write a brief summary or to record specific observations or notes
Planned Value PV or Budgeted Cost of Work Scheduled BCWS
tableWBSTask Name,TBCTask Task Task Task Task Task Insert new rows above this oneTotal Budgeted Cost,Cumulative Planned Vlue PV
Actual Cost and Earned Value
Project Performance Metrics
Cost Variance
Schedule Variance SV EV PV
Cost Performance Index CPI EVAC
Schedule Performance Index SPI EVPV
Estimated Cost at Completion EAC
Esitmate to complete ETCEACAC
Variance at Completion VACBACEAC
table
table
Updated EV and AC for Weeks Through
Tips on Completing the Assignment:
Step : Take a screenshot of the graph and calculate the EAC, ETC, and VAC, then answer Question
Step : Enter the data for Weeks through see below
Step : Take a screenshot of the graph and compare the BAC with the EAC ie look at the VAC at week
and then answer Question
NOTE: Don't forget to update the cumulative AC and EAC in the Actual Cost and Earned Value
rows in the Report tab.Project Title
Company Name Logo
Earned Value Analysis Report
Prepared By: Alex Zylka
Date:
For Period:
Week
Summary:
Use this space to write a brief summary or to record specific observations or notes
Planned Value PV or Budgeted Cost of Work Scheduled BCWS
tableWBSTask Name,TBCTask Task Task Task Task Task
