Question: EX 1 3 - 4 ( Algo ) Given the following project network,... Given the following project network, baseline, and status information, develop status reports

EX13-4(Algo) Given the following project network,...
Given the following project network, baseline, and status information, develop status reports for perlods 2,4,6,8 and and complete the performance Indexes table. Calculate the \(\mathrm{EAC}_{f}\) and the \(\mathrm{VAC}_{\mathrm{f}}\).
(Do not round Intermediate calculations. Enter all answers to \(\mathbf{2}\) decimal precision. Enter PCI-B In percent format (e.g., enter 73.05\% If the decimal equivalent is 0.7305.)(Do not round Intermedate calculations. Enter all answers to 2 declmal precislon. Enter PCI-B In percent format (e.g., enter 73.05\% If the decimal equivalent is 0.7305.)\begin{tabular}{|c|c|c|r|l|l|l|}
\hline \multicolumn{2}{|l|}{ Status Report: Ending Period 8} & & & & & \\
\hline Task & \% Complete & EV & AC & PV & CV & SV \\
\hline A & 100 & & 35.00 & & & \\
\hline B & 100 & & 24.00 & & & \\
\hline C & 100 & & 32.00 & & & \\
\hline D & 33.33 & & 20.00 & & & \\
\hline E & 100 & & 20.00 & & & \\
\hline \multicolumn{4}{|l|}{ Cumulative Totals }\\
\hline
\end{tabular}
\begin{tabular}{|c|c|c|c|c|c|c|c|}
\hline \multicolumn{3}{|l|}{ Performance Indexes Summary } & & & & & \\
\hline Period & EV & \multicolumn{1}{c|}{ AC } & PV & SPI & CPI & PCI-B & \\
\hline 2 & & 37.00 & & & & & \(\%\)\\
\hline 4 & & 59.00 & & & & & \(\%\)\\
\hline 6 & & 93.00 & & & & & \(\%\)\\
\hline 8 & & 131.00 & & & & & \(\%\)\\
\hline
\end{tabular}
EACf \(=\quad \) VACf \(=\)
EX 1 3 - 4 ( Algo ) Given the following project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!