Question: EX 6 - 1 1 ( Algo ) A large Southeast city is requesting federal... A large Southeast city is requesting federal funding for a

EX6-11(Algo) A large Southeast city is requesting federal...
A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a
network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet
this requirement. She has gathered the activity time estimates and their dependencies shown here.