Question: EX 6 - 2 1 ( Algo ) Given the following information, compute... Given the following information, compute the early, late, and slack times for

EX6-21(Algo) Given the following information, compute...
Given the following information, compute the early, late, and slack times for the project network.
ID Task Duration Predecessor Additional Lag Relationships Lag
A Interview users 9
B Define new features 9 A Start-start A to B
Finish-finish A to B 6
5
C Order components 3 B
D Build prototype 6 C Finish-start C to D 7
E Test 6 C Finish-start C to E
Finish-finish D to E 3
4
F Field test 10 E