Question: EX 6 - 2 3 ( Algo ) The CyClon project team has started... The CyClon project team has started gathering the information necessary to
EX Algo The CyClon project team has started...
The CyClon project team has started gathering the information necessary to develop a project networkpredecessor activities and
activity time in days. The results of their meeting are found in the following table:
Part A Draw the project network. Compute the early, late, and slack times for each activity.
Part B Upon further review the team recognize that they missed three finishtostart lags. Procure prototype parts will involve only days of work but it will take days for the parts to be delivered. Likewise, Order stock components will take days of work and days for delivery and Order custom components will take days of work and days for delivery. Reconfigure the CyClon schedule by entering the three finishtostart lags.
What impact did these lags have on the original schedule?
Click to select
What impact did these lags have on the amount of work required to complete the project?
Click to select
Part C Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finishtostart relationships and that it might be possible to reduce project duration by creating starttostart lags. After much deliberation the team concluded that the following relationships could be converted into starttostart lags:
Procure prototype parts could start days after the start of Design.
Fabricate parts could start days after the start of Design.
Laboratory test could begin days after the start of Assemble prototype.
Field test could start days after the start of Laboratory test.
Adjust design could begin days after the start of Field test.
Order stock and Order custom components could begin days and days, respectively, after Adjust design.
Test unit could begin days after the start of Assemble test production unit.
Document results could start days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine starttostart lags.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock