Question: EX 6 - 2 3 ( Algo ) The CyClon project team has started... The CyClon project team has started gathering the information necessary to
EX Algo The CyClon project team has started...
The CyClon project team has started gathering the information necessary to develop a project networkpredecessor activities and activity time in days. The results of their meeting are found in the following table:
Activity Description Duration Predecessor
A Design
B Procure prototype parts A
C Fabricate parts A
D Assemble prototype B C
E Laboratory test D
F Field test E
G Adjust design F
H Order stock components G
I Order custom components G
J Assemble test production unit H I
K Test unit J
L Document results K
Part A Draw the project network. Compute the early, late, and slack times for each activity.
What is the ES for Activity Dselected answer correct
What is the LF for Activity Hselected answer incorrect
What is the slack for Activity Cselected answer correct
What is the slack for Activity Hselected answer incorrect
What is the slack for Activity I? selected answer incorrect
What is the length of the project? selected answer correct time periods.
What is the critical path? A C D E F G I, J K Lselected answer correct
Part B Upon further review the team recognize that they missed three finishtostart lags. Procure prototype parts will involve only days of work but it will take days for the parts to be delivered. Likewise, Order stock components will take days of work and days for delivery and Order custom components will take days of work and days for delivery. Reconfigure the CyClon schedule by entering the three finishtostart lags.
What impact did these lags have on the original schedule? The critical path remains the same Correct
What impact did these lags have on the amount of work required to complete the project? The schedule remains the same Correct
Part C Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finishtostart relationships and that it might be possible to reduce project duration by creating starttostart lags. After much deliberation the team concluded that the following relationships could be converted into starttostart lags:
Procure prototype parts could start days after the start of Design.
Fabricate parts could start days after the start of Design.
Laboratory test could begin days after the start of Assemble prototype.
Field test could start days after the start of Laboratory test.
Adjust design could begin days after the start of Field test.
Order stock and Order custom components could begin days and days, respectively, after Adjust design.
Test unit could begin days after the start of Assemble test production unit.
Document results could start days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine starttostart lags.
What is the ES for Activity Dselected answer correct
What is the LF for Activity Hselected answer incorrect
What is the slack for Activity Cselected answer correct
What is the slack for Activity Hselected answer incorrect
What is the slack for Activity I? selected answer correct
What is the length of the project? selected answer incorrect time periods.
What is the critical path? A C D E F G I, J K Lselected answer correct
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock