Question: EX 8 - 9 ( Static ) You have prepared the following schedule... You have prepared the following schedule for a project in which the
EXStatic You have prepared the following schedule...
You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having three backhoes. You receive a call from your partner, Brooker, who desperately needs one of your backhoes.
You tell Brooker you are willing to let him have the backhoe if you are still able to complete your project in months. Develop a resource schedule to see if it is possible to complete the project in months with only two backhoes.
Activities and require two backhoes, while activities and require one backhoe. No splitting of activities is possible.