Question: EX 9 - 1 ( Static ) Use the information contained below... Use the following information to compress one - time unit per move using
EXStatic Use the information contained below...
Use the following information to compress onetime unit per move using the leastcost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activitys was crashed and the adjusted total cost
Note: The correct normal project duration, critical path, and total direct cost are provided.
tabletableActivityIDtableCrash costSlopetableMaximumCrash TimeABCDEFTotal direct normal costs,
To compress from time period to time crash the following activitysYou may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.
A
B
C
D
E
F
What is the adjusted total cost at time period
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock