Question: EX 9 - 7 ( Static ) Use the information contained below... Use the following information to compress one time unit per move using the
EXStatic Use the information contained below...
Use the following information to compress one time unit per move using the leastcost method. Assume the total indirect cost for the project is $ and there is a savings of $ per time unit reduced. Calculate the total direct, indirect, and project costs for each duration. What is the optimum costtime schedule for the project?
Note: The correct normal project duration and total direct cost are provided.