Question: EX 9 - 8 ( Static ) Use the information contained in the tables... Use the following information to compress one time unit per move

EX9-8(Static) Use the information contained in the tables...
Use the following information to compress one time unit per move using the least-cost method. Reduce the schedule until you reach the crash point of the network.
Activity Crash cost Maximum
ID (Slope) Crash Time Normal time Normal cost
A 003150
B 10014200
C 6013250
D 4014200
E 002250
F 3023200
G 2012250
H 6024300
I 20012200
Total direct normal costs $2,000
The indirect costs for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for 14 weeks, $1,300 for 13 weeks, $1,250 for 12 weeks, $1,200 for 11 weeks, and $1,150 for 10 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!