Question: EX10-3b (Static) When building a stakeholder map, a project... When building a stakeholder map, a project manager should include all people or groups who meet
EX10-3b (Static) When building a stakeholder map, a project... When building a stakeholder map, a project manager should include all people or groups who meet all of the following criteria except which one? Multiple Choice Those who have a positive attitude toward the project. Those whose cooperation is necessary to complete the project. Those who have a low level of interest in the project. Those who oppose the project and may block its completion. Those whose agreement or approval are required for project deliverables