Question: EX6-15 (Static) You are creating a database for the... You are creating a database for the Oklahoma City Thunder NBA basketball team. Given the project

EX6-15 (Static) You are creating a database for

EX6-15 (Static) You are creating a database for the... You are creating a database for the Oklahoma City Thunder NBA basketball team. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project