Question: EX8-11 (Algo) Given the time-phased work... Given the time-phased work packages, complete the baseline budget for the project. Time-phased budget ($ 000) Week Task Week

EX8-11 (Algo) Given the time-phased work... Given
EX8-11 (Algo) Given the time-phased work... Given the time-phased work packages, complete the baseline budget for the project. Time-phased budget ($ 000) Week Task Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Budget Week 1 9 Activity 1 9 Activity 2 23 8 Activity 3 27 9 5 Activity 4 22 9 Activity 5 12 Total 93 Cumulative 9 7 6 6 5 Week 9 Week 10 LUANA 5