Question: Exam # 2 Sample Problem - B 1 Per the superintendent and based on the request by the owner, the scope of work has changed

Exam #2 Sample Problem - B
1 Per the superintendent and based on the request by the owner, the scope of work has
changed and as follows. The owner wants to extend an existing wall Type C by 47 feet. Notingthat
the wall Type C is a 4" metal stud wall with one layer of 58" fire coat sheetrock on one side and two
layers of 58" fire coat sheetrock on the other side with 4-12'' sound insulation in the wall. Thewall
will have acoustical caulking on both sides at the top and bottom. The wall is 13'-3-12 "high andis
anchored to a concrete roof deck above. The painting subcontractor bid a unit cost of $2.39SF for
tape, float and painting of the sheetrocks exposed faces. The wall has one framed opening that is
3'7'. Prove the price to accomplish this work based on the unitsbelow. Note that all the linesshould
be filled in and no holes should remain. All quantities and cost should be rounded to the
nearest whole number.
Exam # 2 Sample Problem - B 1 Per the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!