Question: Exam # 2 Sample Problem - B 1 Per the superintendent and based on the request by the owner, the scope of work has changed
Exam # Sample Problem B
Per the superintendent and based on the request by the owner, the scope of work has
changed and as follows. The owner wants to extend an existing wall Type by feet. Notingthat
the wall Type is a metal stud wall with one layer of fire coat sheetrock on one side and two
layers of fire coat sheetrock on the other side with sound insulation in the wall. Thewall
will have acoustical caulking on both sides at the top and bottom. The wall is "high andis
anchored to a concrete roof deck above. The painting subcontractor bid a unit cost of $ for
tape, float and painting of the sheetrocks exposed faces. The wall has one framed opening that is
Prove the price to accomplish this work based on the unitsbelow. Note that all the linesshould
be filled in and no holes should remain. All quantities and cost should be rounded to the
nearest whole number.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock