Question: EXAMPLE 10.2 A state government is planning a hydroelectric project for a river basin. In addition to the production of electric power, this project will

EXAMPLE 10.2 A state government is planning a hydroelectric project for a river basin. In addition to the production of electric power, this project will provide flood control, irrigation and recreation benefits. The estimated benefits and costs that are expected to be derived from this project are as follows: Initial cost = Rs. 8,00,00,000 Annual power sales = Rs. 60,00,000 Annual flood control savings = Rs. 30,00,000 Annual irrigation benefits = Rs. 50,00,000 Annual recreation benefits = Rs. 20,00,000 Annual operating and maintenance costs = Rs. 30,00,000 Life of the project = 50 years Check whether the state government should implement the project (Assume i = 12%)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts