Question: Example 3 . 1 2 . A project has fourteen activities A through M . The relationships which obtain amongst these activities are given below.

Example 3.12. A project has fourteen activities A through M. The relationships which obtain amongst these activities are given below.
(i)A is the first operation.
(ii)B and C can be performed in parallel and are immediate successor to A.
(iii)D,E and F follow B.
(iv)G follows E.
(v)H follows D, but it cannot start until E is complete.
(vi) I and J succeed G.
(vii)F and J precede K.
(viii)H and I precede L.
(ix)M succeeds L and K.
(x) The last operation N succeeds M and C.
Construct the network diagram.
Example 3 . 1 2 . A project has fourteen

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!