Question: Example 3 . 1 2 . A project has fourteen activities A through M . The relationships which obtain amongst these activities are given below.
Example A project has fourteen activities A through The relationships which obtain amongst these activities are given below.
i is the first operation.
ii and can be performed in parallel and are immediate successor to
iii and follow
iv follows
v follows but it cannot start until is complete.
vi I and succeed
vii and precede
viii and I precede
ix succeeds and
x The last operation succeeds and
Construct the network diagram.