Question: Example: A building project is estimated to have a cost at completion of $ 9 2 0 , 0 0 0 . At the end

Example: A building project is estimated to have a cost at completion of $920,000. At the end of month 4, the external walls were completed & the internal walls were started, and the scheduled cost was $523,000 while the actual cost spent was $540,000. Assuming that internal walls is a long activity (can be reported with 20% progress), and based on the following Incremental Milestone schedule
Calculate at the end of month 4: (Please show your calculations)
1) Earned Value.
2) Schedule & Cost Variance, SPI & CPI.
3) Forecasted cost at completion assuming progress rate to date will prevail in the future.
Milestones
% Complete
Erect structure
20%
Complete roof
40%
Complete external walls
55%
Complete internal walls
70%
Utilities
95%
Hand over
100%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!