Question: Example: A building project is estimated to have a cost at completion of $ 9 2 0 , 0 0 0 . At the end
Example: A building project is estimated to have a cost at completion of $ At the end of month the external walls were completed & the internal walls were started, and the scheduled cost was $ while the actual cost spent was $ Assuming that internal walls is a long activity can be reported with progress and based on the following Incremental Milestone schedule
Calculate at the end of month : Please show your calculations
Earned Value.
Schedule & Cost Variance, SPI & CPI.
Forecasted cost at completion assuming progress rate to date will prevail in the future.
Milestones
Complete
Erect structure
Complete roof
Complete external walls
Complete internal walls
Utilities
Hand over
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock