Question: Example Applymg the TOC Methodology ' Consider a process with 9 activities and three resource types. Activities 1, 2 8: 3 require 10 minutes of

Example Applymg the TOC Methodology ' Consider a process with 9 activities and three resource types. Activities 1, 2 8: 3 require 10 minutes of processing and the other activities 5 minutes each. ' There are 3 jobs, following different paths being processed Job Routing Demand Prot Margin (Units/week) A 4, 8, and 9 50 20 1. 2. 3. 5. 6. B 7, and 8 100 75 2. 3. 4. 5, 6. C 7 8 and 9 60 60 ' Activities 1, 2 8: 3 utilize resource X, activities 4, 5, 81 6 resource Y and activities 7, 8 8: 9 resource Z. Each resource have 2400 minutes of weekly processing time available 30