Question: EXAMPLE PROBLEM A hardware company stocks nuts and bolts and orders them from a local supplier once every 2 weeks ( 1 0 working days

EXAMPLE PROBLEM
A hardware company stocks nuts and bolts and orders them from a local supplier
once every 2 weeks (10 working days). Lead time is 2 days. The company has deter-
mined that the average demand for 12-inch bolts is 150 per week (5 working days), and
it wants to keep a safety stock of 3 days' supply on hand. An order is to be placed this
week, and stock on hand is 130 bolts.
a. What is the target level?
b. How many 12-inch bolts should be ordered this time?