Question: Example: Table shows a contractor's project's activities along with starting and finishing time and the budgeted cost. The conditions of contract allow measurements to be

Example: Table shows a contractor's project's activities along with starting and finishing time and the budgeted cost. The conditions of contract allow measurements to be made monthly and payment of the amount certified less 5% retention to be paid to the contractor after a month. Retention money is to be released after 6 months of completion. Annual interest rate is 15% on locked-up capital. Calculate the total profit of the contractor if he earns 10% profit on quoted cost.
\table[[Activity,Starting month,Duration (month),Cost/month],[F,5,1,200000],[E,3.5,1.5,40000],[D,3,1,150000],[C,3,1.5,120000],[B,1,3,40000],[A,0,2,45000]]
Example: Table shows a contractor's project's

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!