Question: Example The network in the figure is for a project in which the key resources is engineers. The network has been evaluated on the assumption

Example
The network in the figure is for a project in which the key resources is engineers. The network has been evaluated on the assumption that an unlimited number of engineers is available and the duration of the project is then 28 days as shown.
Resource aggregation:
1-draw the histogram showing the demand for engineers if each activity is started:
At the earliest start time
At the latest start time
Schedule the start of each activity if only 3 engineers are available and determine the effect on the project duration.
Assume in this case that no activity can be split.
\table[[Activity,Duration,E.S.,E.F,T.F.,r.r],[A,6,0,0,0,1-
 Example The network in the figure is for a project in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!