6-47. The activities in the following table describe the construction of a new 271se. Construct the associated project network. Activity Predecessor(s) Duration (days) A: Clear site 1 B: Bring utilities to site 2 C: Excavate 1 D: Pour foundation 2 E: Outside plumbing B,C 6 F: Frame house D 10 Activity Predecessor(s) Duration (days) G: H: 1: J: K: L: M: N: O: P: F E,H 1 F,J Do electric wiring Lay floor Lay roof Inside plumbing Shingling Outside sheathing insulation Install windows and outside doors Do brick work Insulate walls and ceiling Cover walls and ceiling Insulate roof Finish interior Finish exterior Landscape LM GJ o I,P P I,N S 3 1 1 5 2 1 2 4 2 2 1 7 7 3 R: S: T